Accounting Problems Five problems and Solutions
1.
Future Value (Year 5) = $10,000 (1.05)5 = $12,762.82
New Balance (Year 5) = $12,762.82 – $7,500 = $5,262.85
Future Value (Year 8) = $5,262.82 (1.05)3 = $6,092.37
2.
PV of $10,000 = $10,000 x 0.3855 = $3,855
PV of Annuity of $400 = $400 x 12.4622 = $4,984.88
Value of Bond = $3,855 + $4,984.88 = $8,839.88
3.
PV of Alternative A = $300 x 4.4873 = $1,346.19
PV of Alternative B = $400 x (0.8696) + $300 (0.5718) + $600 (0.3269) = $715.52
PV of Alternative C = $600 (0.5718) = $343.08
4.
Cost of External Equity = [$1.15 + ($22 x 0.95 x 7%)] / ($22 x 0.95) = 12.50%
5.
a.
NPV of Project A = -$2,000 + $500 (4.4226) = $211.30
NPV of Project B = -$2,000 + $5,650 (0.4251) = $401.42
IRR of Project A = 16.33%
IRR of Project B = 15.99%
c.
Project B should be chosen because it has higher NPV.
b.
Project B is a better option while IRR indicates ProjectA as better option.
The ranking conflict is due to the fact that based on NPV